US 101 Improvements (I-280 to Yerba Buena Rd)

Description: In San Jose, on Route 101, from the I-280/I-680 interchange to north of Yerba Buena Rd.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Clara
City San Jose
Zip Code 95116, 95121, 95122
 
Senate District
13
Assembly District 28
Congressional District 16
 
Caltrans District
04
 
 
County/State Route Santa Clara 101
Postmile Begin/End 31 34.9
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  3530    3530  
Lane Miles Added (HOV)  0      
Peak Period Time Savings (minutes)  281078    281078  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Santa Clara Valley Transportation Authority John Ristow (408) 321-5713   john.ristow@vta.org
Design (PS&E) Phase
Santa Clara Valley Transportation Authority John Ristow (408) 321-5713   john.ristow@vta.org
Right of Way Phase
Santa Clara Valley Transportation Authority John Ristow (408) 321-5713   john.ristow@vta.org
Construction Phase
Caltrans Gene Gonzalo (510) 622-0810   gene_gonzalo@dot.ca.gov
 
Corridor System Management Plan
Caltrans Juliana Gum (510) 286-4579   juliana_gum@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$30,000 $-13,364 $16,636
Non-bond Funding
State/Federal*
$955 $4,356 $5,311
Local**
$32,020 $-4,356 $27,664
Non Budgeted ETC
$0 $0 $0
 
Total**** $62,975 $-13,364 $49,611

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$3,320 $0 $3,320 $4,142
Design(PS&E)
$6,550 $0 $6,550 $8,098
Right of Way
$1,850 $0 $1,850 $2,089
Construction
$51,255 $-13,364 $37,891 $32,666
 
Total* $62,975 $-13,364 $49,611 $42,931

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
08/01/2007 

03/01/2009 
 

 
08/01/2007 

03/01/2009 
100  08/01/2007 

03/26/2009 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2008 

11/01/2009 
 

 
01/01/2008 

11/01/2009 
100  01/01/2008 

03/02/2010 


-4 
Begin Right of Way Phase

End Right of Way Phase
03/01/2009 

11/01/2009 
 

 
03/01/2009 

11/01/2009 
100  03/01/2009 

08/25/2009 


Begin Construction Phase

End Construction Phase
03/01/2010 

12/01/2012 
 

 
09/01/2010 

06/01/2013 
100  11/09/2010 

10/31/2012 
-2 

Begin Closeout Phase

End Closeout Phase
01/01/2013 

01/01/2014 
 

 
06/01/2013 

06/01/2014 
100  10/31/2012 

10/15/2014 


-5 
Corridor System Management Plan
Adoption Date 12/01/2009    12/01/2009  100  12/21/2010  -13 
Implementation Date 12/01/2009    12/01/2009  12/21/2011  -25 
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 3530 3530
Lane Miles Added (HOV) 0
Peak Period Time Savings (minutes) 281078 281078

Bond Funding Cost
Adopted:
$30,000,000
Current Approved:
$16,894,000
Actual Expenditures:
$16,565,000

 

Status as of December 31, 2023.